Question 1
8 marks
1
Using network analysis, the Operations Director estimates the factory expansion and machinery upgrade will take a minimum of 24 weeks.
8 marks
Question 2
8 marks
2
Using network analysis, the Operations Director estimates the factory expansion and machinery upgrade will take a minimum of 24 weeks.
8 marks
Question 3
16 marks
3(a)
Calculate, for 2024, IPA’s market share.
2 marks
3(b)
Calculate, for 2025, the expected percentage market growth.
2 marks
3(c)
Using network analysis, the Operations Director estimates the factory expansion and machinery upgrade will take a minimum of 24 weeks.
12 marks
Question 4
16 marks
4(a)
Complete nodes 5 and 6 on the network diagram below (reproduced from the Insert).
2 marks
4(b)
Calculate the total float for Activity F.
2 marks
4(c)
Using network analysis, the Operations Director estimates the factory expansion and machinery upgrade will take a minimum of 24 weeks.
12 marks
Question 5
12 marks
5
Using network analysis, the Operations Director estimates the factory expansion and machinery upgrade will take a minimum of 24 weeks.
12 marks